Question 16
Which of the following are the key activities with the “Define Portfolio” process?
Evaluating portfolio components with a ranking and scoring model comprising weighted key criteria
Evaluating and determining performance and expected value and benefits (financial and non-financial) of portfolio components
Categorizing portfolio components to which a common set of decision filters and criteria may be applied
Determining resource (human, assets, and technology) capability, resource capacity available, and constraints for portfolio components
Question 17
The above figure shows the relationship between supply and demand. Which area do you want to minimize?
Allocated Resources
Resource Capacity
Resource Requirement
Unused Capacity
Question 18
You have just completed portfolio optimization and want to allocate resources to selected portfolio components. Which process should you follow?
Manage Supply and Demand
Develop Portfolio Management Plan
Provide Portfolio Oversight
Authorize Portfolio
Question 19
After developing a portfolio strategic plan, you create various portfolio scenarios using different combinations of both potential components and current components, evaluating their possible outcomes based on multiple assumptions? Which process are you doing?
Develop Portfolio Charter
Optimize Portfolio
Develop Portfolio Roadmap
Manage Strategic Change
Question 20
Which of the following is not one of the four stages for portfolio risk management?