Question 16
To ensure VM availability when a service outage has occurred, a customer has requested that automatic VM failovers must occur as part of the DR strategy for their environment. Which failover operation is within an Unplanned Failover option?
AHV Metro – with Witness Operation
Test Failover
Protection Domain Migrate
Cross-Cluster Live Migration
Question 17
A customer has requested that a consultant create a Disaster Recovery Test for their new Nutanix environments. What should the consultant include in a custom plan to validate VM availability across the network?
Ensure NTP configuration active.
Verify VMs received correct IP address after failover.