Question 1
Which event triggers the issuance of a certificate of occupancy?
- Construction work is complete except for fire alarm testing.
- The contractor sends you a pay request for 100% complete work.
- The owner wants to move into part of the space before the rest is finished.
- The city inspector has inspected and finalized the job.
Question 2
What factors are MOST important in determining the locations of individual workstations within departments?
- Planning and design concepts
- Company image and employee status
- Work relationships and job adjacencies
- Client's business and communication patterns
Question 3
In which situation should you use a construction change directive?
- To request an electrical contractor not listed by the contractor in the bid [tender] documents
- To request pricing for an additional receptacle per the client's request
- To provide additional dimensions to the contractor regarding a receptacle location
- To relocate an electrical receptacle because of revised furniture plans
Question 4
Why are addenda issued?
- To provide additional information not included in the bid package
- To inform potential bidders about acceptable alternates
- To obtain additional information
- To request a change during construction
Question 5
Which light and color characteristic would be MOST effective to enhance way-finding in a senior living facility?
- Brightness
- Hue
- Contrast
- Saturation