Question 21
Which task will be carried out while performing the 'identify - risks' step?
Calculating when an identified risk is likely to occur
Ranking the importance of the stakeholders involved in the activity
Ensuring that all participants agree on the identified risks
Developing an appropriate response to the identified risks
Question 22
Identify the missing word in the following sentence. The impact of risks to organizational goals at the [ ? ] perspective may only become noticeable far into the future.
strategic
programme
project
operational
Question 23
Which is NOT a recommended risk response option for an 'opportunity'?
Enhance
Transfer
Share
Reduce
Question 24
Which is a purpose of the 'risk management policy'?
Explain the actions required to implement risk management
Define the Specific risk management activities that will be performed for an activity
Describe how risk management practices will be implemented throughout an organization
Record information about threats and opportunities for an organizational activity
Question 25
What is the goal of the 'assess - estimate' step?
Identify the threats and opportunities facing the organizational activity
Estimate and agree the budget required to manage risks to the activity
Assess the effectiveness of the risk management processes within an organization
Determine the risks with the greatest effect on activities objectives