Question 6
Which of the following functions are integrated in the integrated UPS in the FusionModule2000? (Choose all that apply.)
Modular UPS
Equipment room monitoring
Power distribution for cooling equipment
IT cabinet power distribution
Question 7
iSitePower-S can provide customers with uninterruptible power supply. The power-off switching time is less than ( ___ ) ms, and without service interruption.
10
15
25
20
Question 8
Which of the following are the core modules of the FusionDC1000C? (Choose all that apply.)
IT module
Battery module
Power supply module
Cooling module
Question 9
Which of the following statements about Huawei prefabricated modular solution are incorrect? (Choose all that apply.)
Property certificates cannot be obtained for prefabricated modular data centers. Therefore, assets must be depreciated by equipment.
The FusionDC1000C uses the in-row air cooling solution.
For a data center with 1000 cabinets, the TTM of the prefabricated modular construction mode is six months, excluding the time for planning and construction application and design.
By default, the power supply module of the FusionDC1000C outside China includes a transformer.
Question 10
In a large-scale DC, which of the following cooling solutions are used by Huawei in IT equipment rooms? (Choose all that apply.)