Question 16
Which of the following elements facilitates people to know large amounts of information as a picture rather than a table of names and numbers?
Project charter
Organization chart
Risk register
Stakeholder register
Question 17
Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and cost will end. Management has asked Jenny to report and forecast her project's performance based on the Judgmental methods. Which of the following judgmental methods will Jenny use to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.
Scenario building
Autoregressive moving average
Forecast by analogy
Technology forecasting
Question 18
Which of the following are inputs of the Control Scope process?
Requirements documentation
Change request
Project management plan
Work performance information
Question 19
You work as a project manager for HRM Inc. Your project was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1 additional hour. The project must have been completed already. An hourly rate of $100 per hour is provided. Which of the following is the planned value (PV) for the project?
$600
$800
$700
$500
Question 20
Alice is the project manager of the NHQ Project and is entering the project's closing processes. The project, she has managed, has been for another organization in a contractual relationship. Her organization requires Alice to complete performance reviews of the project team, review the deliverables with the project customer, and to obtain formal signoff of the project deliverables. There may be other conditions and activities that Alice likely will need to do in this final project phase. Where can Alice check regarding this project?