Question 61

Amy works as a project manager for HRM Inc. She has to develop a visual diagram which can depict the resources that will be used within the project. Which of the following diagrams will Amy create to accomplish the task?

  1. RACI
  2. Gantt chart
  3. WBS
  4. RBS

Question 62

You are project manager of HHK project. Examine the network diagram given below: A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

  1. Four days
  2. Zero, it is on the critical path.
  3. Six days
  4. Five days

Question 63

Jane works as a project manager for HRM Inc. Various projects are running under her administration. Holly, the team leader of a project, provides Jane the performance indexes of her project. The schedule variance (SV) of her project is 15. What does this figure illustrate?

  1. Holly's project is behind the schedule.
  2. Holly's project is ahead of the schedule.
  3. Holly's project is right on target.
  4. Holly's project has costs that are higher than planned.

Question 64

Which of the following is an input to the identify risks process?

  1. Project scope statement
  2. Residual risks
  3. Return on investment
  4. Referent power

Question 65

You are a new Project Manager who has been entrusted with a project. You have been directing and managing the execution of your project. Which of the following is the most likely outcome as part of this phase of the project?

  1. Approved Deliverables
  2. Lessons learned
  3. Expert Judgment
  4. Project Charter