Question 11
Which of the following measures is a preventive measure?
Installing a logging system that enables changes in a system to be recognized
Shutting down all internet traffic after a hacker has gained access to the company systems
Putting sensitive information in a safe
Classifying a risk as acceptable because the cost of addressing the threat is higher than the value of the information at risk
Question 12
What is a risk analysis used for?
A risk analysis is used to express the value of information for an organization in monetary terms.
A risk analysis is used to clarify to management their responsibilities.
A risk analysis is used in conjunction with security measures to reduce risks to an acceptable level.
A risk analysis is used to ensure that security measures are deployed in a cost-effective and timely fashion.
Question 13
A well executed risk analysis provides a great deal of useful information. A risk analysis has four main objectives. What is not one of the four main objectives of a risk analysis?
Identifying assets and their value
Determining the costs of threats
Establishing a balance between the costs of an incident and the costs of a security measure
Determining relevant vulnerabilities and threats
Question 14
What is an example of a security incident?
The lighting in the department no longer works.
A member of staff loses a laptop.
You cannot set the correct fonts in your word processing software.
A file is saved under an incorrect name.
Question 15
Which of the following measures is a corrective measure?
Incorporating an Intrusion Detection System (IDS) in the design of a computer centre
Installing a virus scanner in an information system
Making a backup of the data that has been created or altered that day
Restoring a backup of the correct database after a corrupt copy of the database was written over the original