CSM-001

CSM-001 practice questions, page 5 of 6, with answer review and explanations.

Question 21

A _____________________ is created during the first half of the Sprint planning meeting and a _________________ is created during the second half of the Sprint planning meeting?

  1. Sprint Backlog, collection of tasks
  2. Product Backlog, collection of tasks
  3. Sprint Goal, Sprint Backlog
  4. Product Backlog, Sprint Backlog

Question 22

The Sprint planning meeting is comprised of how many sections?

  1. 4
  2. 3
  3. 2
  4. 1

Question 23

What is the maximum duration of each Sprint planning meeting section?

  1. 1 hour
  2. 30 minutes
  3. 4 hours
  4. 2 hours
  5. 15 minutes

Question 24

From the activities given, which is the latest step in sequence of the Scrum framework?

  1. Daily scrum
  2. Sprint retrospective
  3. Sprint review
  4. Sprint planning

Question 25

Which of the following is not a Scrum Master responsibility?

  1. Establish priorities together with product owner for Product Backlog items
  2. Preventing Senior Management from shifting team priorities
  3. Empowering the team
  4. Socializing scrum throughout the organization