Question 371
You are the project manager of GHT project. A risk event has occurred in your project and you have identified it. Which of the following tasks you would do in reaction to risk event occurrence? Each correct answer represents a part of the solution. (Choose three.)
Monitor risk
Maintain and initiate incident response plans
Update risk register
Communicate lessons learned from risk events
Question 372
Which of the following parameters would affect the prioritization of the risk responses and development of the risk response plan? Each correct answer represents a complete solution. (Choose three.)
Importance of the risk
Time required to mitigate risk.
Effectiveness of the response
Cost of the response to reduce risk within tolerance levels
Question 373
Which of the following come under the management class of controls? Each correct answer represents a complete solution. (Choose two.)
Risk assessment control
Audit and accountability control
Program management control
Identification and authentication control
Question 374
Which of the following parameters are considered for the selection of risk indicators? Each correct answer represents a part of the solution. (Choose three.)
Size and complexity of the enterprise
Type of market in which the enterprise operates
Risk appetite and risk tolerance
Strategy focus of the enterprise
Question 375
David is the project manager of HRC project. He concluded while HRC project is in process that if he adopts e-commerce, his project can be more fruitful. But he did not engage in electronic commerce (e-commerce) so that he would escape from risk associated with that line of business. What type of risk response had he adopted?