Question 336

You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declined change request be documented and stored?

  1. Change request log
  2. Project archives
  3. Lessons learned
  4. Project document updates

Question 337

Which of the following comes under phases of risk management?

  1. Assessing risk
  2. Prioritization of risk
  3. Identify risk
  4. Monitoring risk
  5. Developing risk

Question 338

You are the project manager in your enterprise. You have identified occurrence of risk event in your enterprise. You have pre-planned risk responses. You have monitored the risks that had occurred. What is the immediate step after this monitoring process that has to be followed in response to risk events?

  1. Initiate incident response
  2. Update the risk register
  3. Eliminate the risk completely
  4. Communicate lessons learned from risk events

Question 339

You are the project manager for GHT project. You need to perform the Qualitative risk analysis process. When you have completed this process, you will produce all of the following as part of the risk register update output except which one?

  1. Probability of achieving time and cost estimates
  2. Priority list of risks
  3. Watch list of low-priority risks
  4. Risks grouped by categories

Question 340

You have been assigned as the Project Manager for a new project that involves building of a new roadway between the city airport to a designated point within the city. However, you notice that the transportation permit issuing authority is taking longer than the planned time to issue the permit to begin construction. What would you classify this as?

  1. Project Risk
  2. Status Update
  3. Risk Update
  4. Project Issue