Question 241

Tom works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks, and provides a quantitative assessment of the likely cost to complete the scheduled activities?

  1. Activity duration estimates
  2. Risk management plan
  3. Cost management plan
  4. Activity cost estimates

Question 242

Which of the following baselines identifies the specifications required by the resource that meet the approved requirements?

  1. Functional baseline
  2. Allocated baseline
  3. Product baseline
  4. Developmental baseline

Question 243

Which of the following nodes of the decision tree analysis represents the start point of decision tree?

  1. Decision node
  2. End node
  3. Event node
  4. Root node

Question 244

You are the project manager of the NHH Project. You are working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team. What document do you and your team is creating in this scenario?

  1. Project plan
  2. Resource management plan
  3. Project management plan
  4. Risk management plan

Question 245

Where are all risks and risk responses documented as the project progresses?

  1. Risk management plan
  2. Project management plan
  3. Risk response plan
  4. Risk register