Question 136

You are the project manager of GFT project. Your project involves the use of electrical motor. It was stated in its specification that if its temperature would increase to 500 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. If the machine overheats even once it will delay the project's arrival date. So to prevent this you have decided while creating response that if the temperature of the machine reach 450, the machine will be paused for at least an hour so as to normalize its temperature. This temperature of 450 degrees is referred to as?

  1. Risk identification
  2. Risk trigger
  3. Risk event
  4. Risk response

Question 137

Which of the following decision tree nodes have probability attached to their branches?

  1. Root node
  2. Event node
  3. End node
  4. Decision node

Question 138

Which of the following IS processes provide indirect information? Each correct answer represents a complete solution. (Choose three.)

  1. Post-implementation reviews of program changes
  2. Security log monitoring
  3. Problem management
  4. Recovery testing

Question 139

You are the risk professional of your enterprise. You need to calculate potential revenue loss if a certain risks occurs. Your enterprise has an electronic (e- commerce) web site that is producing US $1 million of revenue each day, then if a denial of service (DoS) attack occurs that lasts half a day creates how much loss?

  1. US $250,000 loss
  2. US $500,000 loss
  3. US $1 million loss
  4. US $100,000 loss

Question 140

Which of the following process ensures that extracted data are ready for analysis?

  1. Data analysis
  2. Data validation
  3. Data gathering
  4. Data access