CRISC Practice Test practice questions, page 23 of 76, with answer review and explanations.
Question 111
You are the risk official of your enterprise. You have just completed risk analysis process. You noticed that the risk level associated with your project is less than risk tolerance level of your enterprise. Which of following is the MOST likely action you should take?
Apply risk response
Update risk register
No action
Prioritize risk response options
Question 112
Which of the following operational risks ensures that the provision of a quality product is not overshadowed by the production costs of that product?
Information security risks
Contract and product liability risks
Project activity risks
Profitability operational risks
Question 113
Which of the following is the process of numerically analyzing the effects of identified risks on the overall enterprise's objectives?
Identifying Risks
Quantitative Risk Assessment
Qualitative Risk Assessment
Monitoring and Controlling Risks
Question 114
Which of the following processes is described in the statement below? "It is the process of exchanging information and views about risks among stakeholders, such as groups, individuals, and institutions."
Risk governance
IRGC
Risk response planning
Risk communication
Question 115
Which of the following are the principles of risk management? Each correct answer represents a complete solution. (Choose three.)
Risk management should be an integral part of the organization
Risk management should be a part of decision-making
Risk management is the responsibility of executive management
Risk management should be transparent and inclusive