Question 86
You work as the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?
Risk Management Plan
Stakeholder management strategy
Communications Management Plan
Resource Management Plan
Question 87
Your project spans the entire organization. You would like to assess the risk of your project but worried about that some of the managers involved in the project could affect the outcome of any risk identification meeting. Your consideration is based on the fact that some employees would not want to publicly identify risk events that could declare their supervision as poor. You would like a method that would allow participants to anonymously identify risk events. What risk identification method could you use?
Delphi technique
Root cause analysis
Isolated pilot groups
SWOT analysis
Question 88
Which of the following represents lack of adequate controls?
Vulnerability
Threat
Asset
Impact
Question 89
The only output of qualitative risk analysis is risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?
Trends in qualitative risk analysis
Risk probability-impact matrix
Risks grouped by categories
Watchlist of low-priority risks
Question 90
Which of the following risks is the risk that happen with an important business partner and affects a large group of enterprises within an area or industry?