Question 86

You work as the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?

  1. Risk Management Plan
  2. Stakeholder management strategy
  3. Communications Management Plan
  4. Resource Management Plan

Question 87

Your project spans the entire organization. You would like to assess the risk of your project but worried about that some of the managers involved in the project could affect the outcome of any risk identification meeting. Your consideration is based on the fact that some employees would not want to publicly identify risk events that could declare their supervision as poor. You would like a method that would allow participants to anonymously identify risk events. What risk identification method could you use?

  1. Delphi technique
  2. Root cause analysis
  3. Isolated pilot groups
  4. SWOT analysis

Question 88

Which of the following represents lack of adequate controls?

  1. Vulnerability
  2. Threat
  3. Asset
  4. Impact

Question 89

The only output of qualitative risk analysis is risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?

  1. Trends in qualitative risk analysis
  2. Risk probability-impact matrix
  3. Risks grouped by categories
  4. Watchlist of low-priority risks

Question 90

Which of the following risks is the risk that happen with an important business partner and affects a large group of enterprises within an area or industry?

  1. Contagious risk
  2. Reporting risk
  3. Operational risk
  4. Systemic risk