Question 66

You are the project manager of a project in Bluewell Inc. You and your project team have identified several project risks, completed risk analysis, and are planning to apply most appropriate risk responses. Which of the following tools would you use to choose the appropriate risk response?

  1. Project network diagrams
  2. Cause-and-effect analysis
  3. Decision tree analysis
  4. Delphi Technique

Question 67

You are the risk official of your enterprise. Your enterprise takes important decisions without considering risk credential information and is also unaware of external requirements for risk management and integration with enterprise risk management. In which of the following risk management capability maturity levels does your enterprise exists?

  1. Level 1
  2. Level 0
  3. Level 5
  4. Level 4

Question 68

Which of the following is the priority of data owners when establishing risk mitigation method?

  1. User entitlement changes
  2. Platform security
  3. Intrusion detection
  4. Antivirus controls

Question 69

What type of policy would an organization use to forbid its employees from using organizational e-mail for personal use?

  1. Anti-harassment policy
  2. Acceptable use policy
  3. Intellectual property policy
  4. Privacy policy

Question 70

Wendy has identified a risk event in her project that has an impact of $75,000 and a 60 percent chance of happening. Through research, her project team learns that the risk impact can actually be reduced to just $15,000 with only a ten percent chance of occurring. The proposed solution will cost $25,000. Wendy agrees to the $25,000 solution. What type of risk response is this?

  1. Mitigation
  2. Avoidance
  3. Transference
  4. Enhancing