CRISC Practice Test practice questions, page 10 of 76, with answer review and explanations.
Question 46
A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?
Transference
Mitigation
Avoidance
Exploit
Question 47
John works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk?
Activity duration estimates
Activity cost estimates
Risk management plan
Schedule management plan
Question 48
Which of the following events refer to loss of integrity? Each correct answer represents a complete solution. (Choose three.)
Someone sees company's secret formula
Someone makes unauthorized changes to a Web site
An e-mail message is modified in transit
A virus infects a file
Question 49
Which of the following should be PRIMARILY considered while designing information systems controls?
The IT strategic plan
The existing IT environment
The organizational strategic plan
The present IT budget
Question 50
Which of the following is the MOST effective inhibitor of relevant and efficient communication?
A false sense of confidence at the top on the degree of actual exposure related to IT and lack of a well-understood direction for risk management from the top down
The perception that the enterprise is trying to cover up known risk from stakeholders
Existence of a blame culture
Misalignment between real risk appetite and translation into policies