Question 1
Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?
‘Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change’.
‘Enable altering of planned date for task in WIP/Closed’.
‘Rollup project start date from tasks’.
‘Calculate ROI percentage based on a project's estimated cost and its net value’.
Question 2
Which statement defines the Project Workspace?
A central location to view of all projects in a portfolio to prioritize work
A central location for creating and managing projects
A central location for viewing and assessing business demands
A central location transform the navigation of lists and forms into an interactive graphical experience
Question 3
If a sub-project and parent project have different project currencies, this property should be set to true for cost roll-ups.
com.snc.project.rollup_project_start_date
com.snc.project.calculate_roi
com.snc.project.multicurrency.rollup_if_different
com.snc.project.copy.additional_attributes
Question 4
When can a user choose from multiple rate types for their work, while logging a time card?
Only if this capability is enabled in the Project Record
Only one (1) rate type can apply
Only if the capability is enabled in the Time Sheet Policies
Only if the capability is enabled in the Project Preferences
Question 5
If Scenario Planning for PPM is installed, a portfolio manager can access the Portfolio Planning Workbench by navigating to which of the following? (Choose two.)