CFE

CFE practice questions, page 7 of 7, with answer review and explanations.

Question 31

Which of the following is NOT the reason to bribe employees of the purchaser?

  1. To ensure receipt of a late bid
  2. To extend the bid opening date
  3. To ensure bid-splitting
  4. To falsify the bid log

Question 32

Placing any restriction in the solicitation documents that tend to restrict competition is called prebid solicitation.

  1. True
  2. False