CBAP Practice Test practice questions, page 13 of 20, with answer review and explanations.
Question 61
Which of the following is concerned with determining whether the information used for risk analysis is probable, of high class, or accurate?
Risk Urgency Assessment
Risk Probability and Impact Assessment
Risk Categorization
Risk Data Quality Assessment
Question 62
You are working with several business analysts to determine the solution approach for an identified problem. All of the following techniques are acceptable for identifying the solution approach except for which one?
Benchmarking
Decision analysis
Risk analysis
Brainstorming
Question 63
You are the business analyst for your organization and are in the process of creating the solution approach for a technology problem. Which one of the following definitions best describes the solution approach?
It is the documentation and control of changes to the product scope as approved by the project stakeholders.
Defines the general approach that will be taken to create or acquire new capabilities required to meet the business need.
It is an uncertain event or condition that may have a positive or negative impact on the abilities of the chartered project.
Decomposes the project scope into smaller deliverables; each deliverable is subdivided repeatedly until the deliverable cannot or should not be broken down any further.
Question 64
You are the business analyst for your organization. You are currently working with Steve on the organize requirements process. You and Steve have elected to use the user stories approach for this process. What is the user stories approach for requirements organization?
Stakeholders' experiences equate to the stakeholder requirements.
Stakeholders are interviewed and their experiences are recorded to help identify the requirements.
Stakeholders' objectives are described to identify the requirements that the solution will need to support.
Stakeholders are interviewed and their stories are recorded as part of the requirements.
Question 65
Which of the following processes is used to make certain that the project team members are completing the project work according to the project plan?