CAP Practice Test practice questions, page 11 of 16, with answer review and explanations.
Question 51
In which of the following phases of the DITSCAP process does Security Test and Evaluation (ST&E) occur?
Phase 2
Phase 3
Phase 1
Phase 4
Question 52
You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?
Risk-related contract decisions
Project document updates
Risk register updates
Organizational process assets updates
Question 53
Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?
Configuration management system
Change log
Scope change control system
Integrated change control
Question 54
Which of the following assessment methodologies defines a six-step technical security evaluation?
OCTAVE
FITSAF
DITSCAP
FIPS 102
Question 55
You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?