Question 26
Which statement is true related to job plan revisions?
A job plan must be in a status of DRAFT or PNDREV for updates and edits to the job plan tab.
When a job plan is revised, all existing work orders with the job plan attached are updated with the revised version.
Caution must be used to select the most recent job plan revision when applying a job plan to a work order or preventive maintenance record.
When a job plan has been revised, IBM Maximo Asset Management V7.5 tracks all changes from previous versions. These changes are available for viewing
Question 27
What can be defined on a work order?
Name
Location
Security Group
Report Template
Question 28
Which contract type defines the agreement to maintain one or more assets with an outside service provider for a fee or a scheduled set of payments?
Service Contract
Warranty Contract
Purchase Contract
Labor Rate Contract
Question 29
Which option attaches an image to an item master record in the Item Master application?
Clicking on the Image icon
Clicking on the Attachments icon
Select Action > Add/Modify Image
Select Action > Attachment/Library Folders
Question 30
When a work order is created from a preventive maintenance record that references a route, the route stops will become child work orders with a common job plan. From which record will the resulting parent work order description be created?
It will be the same as the route description.
It will be the same as the job plan description.
It will be null, to be updated with a description specific to the job.
It will be the same as the preventive maintenance record description.