Question 16

A company has a requirement to share calendar, classification, job plan, item description and PM data. What needs to be created?

  1. Single organization, single site environment
  2. Multiple organizations with a shared site environment
  3. Multiple organizations with one site per organization environment
  4. Multiple organizations with multiple sites per organization environment

Question 17

An engineer schedules a very complex asset report developed in BIRT. The engineer needs to set a feature to be able to retrieve the report contents from within Maximo for very large files that are restricted by the email server. Which feature does this?

  1. Direct Print
  2. Email with a File URL
  3. Email with a File Attachment
  4. REPORTSCHEDULE cron task

Question 18

A company has a requirement to have labor certificates defined. In which application can this be done?

  1. Crews
  2. People
  3. Certifications
  4. Qualifications

Question 19

A master PM can be used to do which of the following?

  1. Create a job plan revision.
  2. Generate work orders for associated PMs.
  3. Create associated PMs for an item's location.
  4. Change the status of work orders generated from associated PMs.

Question 20

An administrator has a requirement to ensure that purchase requisitions have been approved before being able to create purchase orders from them. Which settings control this behavior?

  1. Clear the Allow PO Creation From Unapproved PR? checkbox in Purchasing Options.
  2. Clear the Allow PO Creation From Unapproved PR? checkbox on the purchase requisition.
  3. Check the Require PR Approval on PO Creation? checkbox during the creation of the purchase requisition.
  4. Check the purchasing option Require Approval to Convert PR to PO or Contract? (checkbox in Purchasing.