Question 6

What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?

  1. Keeping high priority features at the top of the Product Backlog.
  2. Not allowing changes to the Product Backlog once the Sprint begins.
  3. Supporting the team's decisions and resolving the team's issues.

Question 7

A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint. Who may best prepare this report?

  1. The Product Owner
  2. The Scrum Master
  3. The team
  4. This type of report should not be prepared.

Question 8

Who should update the work estimates during the Sprint?

  1. Only the team members
  2. The Project Manager
  3. The Product Owner

Question 9

Which means of communication is the most preferable to clarify the interpretation of a requirement?

  1. E-mail
  2. Face-to-face
  3. Instant messaging
  4. Telephone

Question 10

In a Scrum project, when would a requirement get added to the Product backlog?

  1. When it is developed, but cannot yet be released.
  2. When the team works on it for a particular release.
  3. When the customer requests a new requirement.