Question 6
Refer to the exhibit. ACME Mining has four data centers in Santiago, Cape Town, Mumbai, and Beijing, full-mesh connected via a 400 Mb/s EVP-LAN. They want to deploy a new mission-critical application with these requirements: * cluster heartbeat 2 MB/s continuous (250 KB/s) * cluster heartbeat one-way maximum latency 100 ms These are the current ping tests results between the four data centers: Which hosting data center pair can host the new application?
Mumbai and Beijing
Cape Town and Mumbai
Cape Town and Beijing
Santiago and Mumbai
Santiago and Beijing
Santiago and Cape Town
Question 7
Refer to the table. A customer investigates connectivity options for a DCI between two production data centers to aid a large-scale migration project. The solution must provide a single 10G connection between locations and be able to run its own varying QoS profiles without service provider interaction based on the migration stages. All connectivity methods are at 10 Gbps. Which transport technology costs the least if the connectivity is required for just one year?
DWDM over dark fiber
Metro Ethernet
MPLS wires only
CWDM over dark fiber
Question 8
Refer to the table. A customer investigates connectivity options for a DCI between two production data centers. The solution must provide dual 10G connections between locations with no single points of failure for Day 1 operations. It must also include an option to scale for up to 20 resilient connections in the second year to accommodate isolated SAN over IP and isolated dedicated replication IP circuits. All connectivity methods are duplex 10 Gbps. Which transport technology costs the least over two years in this scenario?
CWDM
DWDM
MPLS
Metro Ethernet
Question 9
What are two examples of business goals to be considered when a network design is built? (Choose two.)
integrate endpoint posture
ensure faster obsolescence
minimize operational costs
reduce complexity
standardize resiliency
Question 10
Refer to the table. A customer investigates connectivity options for a DCI between two production data centers to aid a large-scale migration project. The migration is estimated to take 20 months to complete but might extend an additional 10 months if issues arise. All connectivity options meet the requirements to migrate workloads. Which transport technology provides the best ROI based on cost and flexibility?